Second Street Construction Update #5

Hello Langley, As we finish up the 8th week of construction we are close to finishing the underground utility work.  The crew is currently installing the stormwater system on Cascade Avenue.  The relocation of the overhead utilities is complete and the majority of the underground utility work is complete.  The new water line has been…

Second Street Construction Update #4

As March begins we are entering into our seventh week of construction on the project.  The transfer of water services to the new water main was completed last week.  We originally thought we could isolate portions of the water main so that only a limited number of connections would be disrupted at a time and…