IMG_20140516_074947

Second Street Construction Update #9

Hello Langley, Project Overview We are in the final month of the project with completion expected during the second week of June.  Only a few small areas of sidewalk remain to be poured at the east and west ends of the project along with the crosswalks at the Anthes and Cascade Intersections.  The rain garden…

IMG_20140423_083035 (1)

Second Street Construction Update #8

Hello Langley, We are wrapping up week 14 of the Second Street Project and the finish line is in sight.  The project remains on schedule with completion estimated for the first part of June. The last panel of the concrete street section was poured on Thursday April 24th.  The remaining concrete work includes the stamped concrete…

Screen Shot 2014-03-28 at 9.49.26 AM

Second Street Construction Update #7

Hello Langley, The project is taking shape!  The rain garden has been formed, the seat-walls are up, the plaza concrete base is poured and we even have a small section of sidewalk installed (with the exception of the scoring) at the west end.  We are two months away from the estimated completion date and the…

Screen Shot 2014-03-28 at 9.49.26 AM

Second Street Construction Update #6 + Design Plans

Hello Langley, First, a big thank you to everyone involved in putting on the very successful Monsters on Machines Event last Saturday.  Special thanks go to Langley Main Street, South Whidbey Commons, SRV Construction, Moonraker Books and local author Deb Lund (author of Monsters on Machines children’s book) for planning and participating in the event.…

watercolor-perspective1.jpg

Second Street Construction Update #5

Hello Langley, As we finish up the 8th week of construction we are close to finishing the underground utility work.  The crew is currently installing the stormwater system on Cascade Avenue.  The relocation of the overhead utilities is complete and the majority of the underground utility work is complete.  The new water line has been…

Second Angled Parking Street

Second Street Construction Update #3

We are officially a month into the project construction and we remain on schedule with no major issues to report.  Water services will be converted to the new waterline next week and Puget Sound Energy has begun the installation process for moving the overhead utilities, which will continue next week.  The excavation of the sidewalk…

second street construction photo 2

Second Street Construction Update #2

Hello Langley.  Here is the latest information the Second Street Project.  In general, the project is moving along as planned without any major construction issues.  The city very much appreciates the support and cooperation from the community to make this project a success. Construction Schedule The contractor is currently installing the new water main on…

Second Street Logo v4 reduced

Second Street Project Open House

The City of Langley will host an open house on Tuesday January 14th at 5:30pm at City Hall to review the Second Street Project in advance of the start of construction scheduled to begin on or near January 20, 2014.  The purpose of the meeting is to provide an overview of the project, review the…

Second Street Logo v4 reduced

Second Street Project Funding

Following a year of planning and discussion the Second Street Project funding was finalized at the Monday December 16th city council meeting along with the approval of the 2014 budget.  The total project cost is approximately $2.2 million dollars of which approximately $1.4 million is being funded through federal and state grants.  The stormwater and…

Watercolor Perspective

Second Street Project Construction and Plan

The City Council approved the contract for the Second Street Project at the meeting on Monday, December 2nd.  The contractor for this project will be SRV Construction out of Oak Harbor.  We will be holding our pre-construction meeting on December 18th to review the schedule of work in order to provide the most accurate and…